QUESTION NO: 1
You need to resolve the performance issue reported by the users in the priv1 region.
What should you do?

Correct Answer: D Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 2
You need to change the DNS forwarder of the priv1 region.
Which two actions should you perform? Each correct answer presents part of the solution?
NOTE: Each correct selection is worth one point.

Correct Answer: A,C Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 3
You have 20 computers that run Linux.
You deploy a disconnected Azure Stack Hub integrated system.
You need to ensure that users on the Linux computers can manage their Azure Stack Hub resources by using Azure Command-Line Interface (CLI).
What should you do first?

Correct Answer: D Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 4
You have an Azure Stack Hub integrated system linked to an Azure AD tenant.
You need to back up virtual machines in user subscriptions. The solution must meet the following requirements:
Back up running virtual machines.
Maximize resiliency.
What should you use?

Correct Answer: C Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 5
You deploy an Azure Stack Hub integrated system that contains an Azure App Service deployment. The integrated system uses an Azure Active Directory (Azure AD) identity provider.
You need to provide users with the ability to deploy App Service web apps directly from their GitHub repositories.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Correct Answer:

Explanation

Reference:
https://docs.microsoft.com/en-us/azure-stack/operator/azure-stack-app-service-configure-deployment-sources?vi
QUESTION NO: 6
You have an Azure Stack Hub integrated system that was recently moved to a new datacenter and powered on.
You need to verify whether the infrastructure components are fully operational.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

Correct Answer: B,C,D Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 7
You need to create a certificate for the Event Hubs resource provider. The solution must support the planned changes.
How should you configure the certificate? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Correct Answer:

Explanation
Box 1: Subject Alternative Name
Implement the App Service resource provider and the Event Hubs resource provider on the integrated system/ Only the Subject Alternative Name is used.

Box 2: DNS Name = =*.eventhub.east.azurestack.treyresearch.net
Event Hubs prerequisites
Procure public key infrastructure (PKI) SSL certificates for Event Hubs. The Subject Alternative Name (SAN) must adhere to the following naming pattern: CN=*.eventhub.<region>.<fqdn>. Subject Name may be specified, but it's not used by Event Hubs when handling certificates. Only the Subject Alternative Name is used. See PKI certificate requirements for the full list of detailed requirements.
Reference:
https://learn.microsoft.com/en-us/azure-stack/operator/event-hubs-rp-prerequisites
QUESTION NO: 8
You need to configure the Azure Stack Hub infrastructure backups. The solution must meet the Azure Stack Hub requirements.
What should you do in the Azure Stack Hub administrator portal? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Correct Answer:

Explanation
Box 1: 4
The infrastructure of the integrated system must be backed up as frequently as possible.
Enable backup for Azure Stack Hub from the administrator portal
The frequency in hours determines how often backups are created. The default value is 12. Scheduler supports a maximum of 12 and a minimum of 4.
Box 2: Azure key vault
The integrated system backups must be retained for 28 days.
Online retention policy. This specifies the time period during which daily, weekly, monthly, and yearly backups are retained in the Azure Site Recovery vault that's associated with the local MABS instance.
Reference:
https://learn.microsoft.com/en-us/azure-stack/operator/azure-stack-backup-enable-backup-console
https://learn.microsoft.com/en-us/azure/architecture/hybrid/azure-stack-backup
QUESTION NO: 9
You start the update of an Azure Stack Hub integrated system. The Update run details are shown in the following exhibit.

Use the drop-down menus to select the answer choice that completes each statement based on the information presented in the graphic.
NOTE: Each correct selection is worth one point.
Correct Answer:

Explanation

Reference:
https://docs.microsoft.com/en-us/azure-stack/operator/azure-stack-apply-updates?view=azs-2008
QUESTION NO: 10
You have an Azure Stack Hub integrated system.
You need to create a new offer that can be used only by an operator to provision user subscriptions. The solution must simplify the process for users to create resources.
Which type of offer should you create?

Correct Answer: B Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 11
You need to identify the PEP information for the integrated system in Chicago. The solution must meet the technical requirements.
What should you use?

Correct Answer: A Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 12
You have a disconnected Azure Stack Hub integrated system.
You plan to implement an app named App1.
You need to create a new service principal for App1. The solution must maximize security.
What should you do first?

Correct Answer: C Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 13
You have an Azure Stack Hub integrated system that is enabled for mufti-tenancy. The integrated system is configured as shown in the following table.

You need lo onboard fabrikam.com as a guest Azure AD tenant to the integrated system.
How should you complete the Power Shell script? To answer, drag the appropriate values to the correct targets. Each value may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Correct Answer:

Explanation

QUALITY AND VALUE

Actual4test Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our Actual4test testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

Actual4test offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.