An administrator is creating several LPARs on a new Power Systems server. The administrator knows that Live Partition Mobility (LPM) will be used to distribute the workload between this new machine and several others in the environment. In addition to ensuring all storage is allocated through Virtual IO servers, what else must the administrator take into consideration when creating the new LPARs?
An administrator has configured NTP on the HMC using the hostname of a public NTP server and restarts the HMC. When the /var/log/ntp file is checked, the synchronization with the time server has not occurred. What is the most likely cause?
When planning a deployment what should be noted about the Virtual Media Repository when compared to other storage visualization offered by a VIO Server?
An administrator has created a virtual media repository to hold images for a file backed virtual optical device. The administrator would now like to load an ISO image, aix7.iso into the repository.
Which of the following commands will achieve this?
An architect is planning to use an existing NIM server to back up and restore VIO server partitions. In addition to the backup of the VIO Server (VIOS), what is needed to successfully complete a restore operation?
An architect is considering whether to specify vSCSI or NPIV for the rootvg disks in a new virtualized environment. Storage is to be provided by an IBM San Volume Controller (SVC) and controlled using SDDPCM.
Which of the following is an advantage of using vSCSI technology instead of NPIV?
A company wants to migrate an existing x86 Linux CRM and database environment from a large cluster of servers to a Power 750 server. How can they perform this with minimal costs and rapid deployment?
A VIO client is using a virtual network adapter to supply network connectivity to VLAN 10 from VIOL The VIO client now needs to access VLAN 20 which is supplied from VI02.
How can this be achieved?
An administrator has a Power 770 with 5 application LPARs and 1 LPAR used by the backup system. The administrator is designing the backup network for this system.
What is a major advantage using Virtual Ethernet compared to using Dedicated Adapters, especially in relation to backups?
An administrator has an application running in a WPAR on a Power 720. The application must be migrated to another server. What is the minimum required hardware level for this to work?
An administrator is planning to update a server managed with Integrated Visualization Manager (IVM) from version 1.5 to version 2.2.
Which of the following statements should the administrator take into consideration?
What configuration change must be made on a Power Systems server to allow a Host Ethernet Adapter (HEA) to be used as part of a Shared Ethernet Adapter (SEA) on a Virtual I/O Server?
A Power Systems server is configured with a VIO server and several client LPARs. The administrator wants to use the padmin user to create a script, which will run on the VIO server to back it up to a remote system. Script output must be collected. How can this be achieved?
A customer is consolidating two POWER6 595 servers to a single Power 795. The two 595 servers each have 24 active processors and have the following LPARs using dedicated processors, running continuously:

The new Power 795 system will have two Processor Books (nodes), each with 8 cores activated in all MCMs (Multi Chip Modules).
LPAR1 is in need of more processing power. If all the other LPARs keep their existing Processor allocation, what is the maximum number of processors which can be allocated to LPAR1?