You are the production planner for a manufacturing company.
After running operations scheduling for a production order, the following error message displays:

You need to identify the cause of the error.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Note: This question is part of series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.
You need to ensure that the system is set up to support the manufacturing process.
Solution: Create a formula version for each concentration level.
Does the solution meet the goal?
A company manufactures automobile engines.
You must create product configurations for values that are used in different types of engines. Each value is based on a master valve design. Different gaskets and fittings are used to allow valves to work with different engines.
You need to translate production plans into Dynamics 365 Finance and Operations elements.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company uses Dynamics 365 Supply Chain Management to manage production configuration.
A product designer creates a remote control toy that can be purchased with different tire sizes.
Sales representatives need to perform product configuration for the custom tire variants when they create a new order.
Solution: Select the custom tire size when filling out the item requirement line.
Does the solution meet the goal?
A manufacturer produces HDMI cables. Typically, the item is manufactured.
The manufacturer will occasionally buy unbranded HDMI cables from a vendor in order to keep up with demand. The company must use the same item number whether they make or buy the item.
What should you do?
A manufacturer uses discreet orders and manually consumes raw material after reporting products as finished.
You are performing an end-of-month closing for remaining picking lists on production orders. You must not be required to consume the full amount of material on production order picking lists as a result of improved production efficiency. When the production manager verifies that no material is left to consume, there are remaining back-ordered amounts.
You need to pick the line item short and eliminate the remaining demand.
What should you do?
A manufacturer sends wiring harnesses to a vendor to be soldered to a connector. You have created the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.
You create separate subcontracting purchase orders to account for the service. You attempt to add the service item to the BOM. The system generates an error.
You need to set up a new item model group for the service item.
Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


1 - Create a new item model group and select stocked product option.
2 - Assign the item model group and select the stocked product option
3 - Add the service item to the BOM
You are building the Bill of materials (BOM) for a new production item. The new item has a subcomponent.
Subproduction orders for the subcomponent must be created when estimating production orders.
You need to configure the BOM line to generate subproduction orders.
Which BOM line type should you use?
A glass bottle manufacturer uses route operations to schedule resources and track manufacturing costs.
The company has recently seen an increase in demand and purchases another resource. The company uses the same costs per resource. However, the new resource costs more to run. The company must be able to track cost contributions for the new resource.
You need to create a cost category for the new resource.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
NOTE: Each correct selection is worth one point.


1 - Create a new cost group
2 - Create a new cost category
3 - Assign the cost category to all route operations that use new resource
You are a functional consultant for Contoso Entertainment System USA (USMF).
You need to configure the system to ensure that planned master orders generated by Material Requirements Planning (MRP) contain trade agreements.
To complete this task, sign in to Dynamics 365 portal.
Explanation:
Navigate to the Master Planning Parameters form (Master Planning > Setup > Master Planning Parameters).
Select the Planned Orders tab.
Select the Find Trade Agreements option.
Save the changes.
Reference:
https://docs.microsoft.com/en-us/learn/modules/configure-use-master-planning-dyn365-supply-chain-mgmt/03-parameters
You need to resolve the issue for UserF.
What should you configure? To answer, select the appropriate options in the answer area.


NOTE: Each correct selection is worth one point.