Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

Suggested Answer: B Vote an answer

by RP at Jul 13, 2024, 05:07 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
RP
2024-07-13 17:07:49
Selected Answer: C
A non-compensable delay can still be excusable (e.g., weather), which would result in a time extension.