Question #: 196
Topic #: 3
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

Suggested Answer: C Vote an answer

* Schedule Update Procedures:
Accurate schedule updates rely on entering actual data (start/finish dates, durations) and evaluating impacts of changes.
"Downstream" logic revisions may be needed but are less critical compared to ensuring accurate historical data and reflecting immediate changes.
* PSP Study Guide Reference:
Schedule updating emphasizes capturing accurate historical data and estimating remaining durations accurately​.
* Analysis of Options:
Option A and B: Key to progress tracking and forecasting.
Option D: Essential for reflecting impacts of delays and change orders.
Option C: While important, downstream logic revisions are less immediate compared to other procedures.
* Conclusion: The correct answer is C, as downstream logic revisions are less critical in achieving an accurate schedule forecast compared to other updates

by laura_lct911 at Apr 16, 2026, 12:07 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.