Exam AACE-PSP Topic 3 Question 92 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 92
Topic #: 3
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

Suggested Answer: C Vote an answer

by Marshall at May 17, 2024, 02:35 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.