Which of the following will always describe the critical path? The path with

Suggested Answer: B Vote an answer

A
* Critical Path Characteristics:
The critical path is the sequence of activities that determines the overall project duration.
It represents the longest duration path through the network and typically has zero float unless delays or constraints introduce negative float.
* PSP Study Guide Reference:
Critical path analysis is a foundational concept in schedule management, as covered extensively in the PSP guide​.
* Analysis of Options:
Option A: Correct. The critical path always has the longest duration.
Option B: Zero float is common but not universal due to constraints or delays.
Option C and D: Negative float describes specific scenarios but does not define the critical path universally.
* Conclusion: The correct answer is A, as the critical path is the longest-duration path through the network.

by vasikhali at May 22, 2026, 01:30 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
vasikhali
2026-05-22 01:30:11
a correct
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.