Exam AACE-PSP Topic 4 Question 32 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 32
Topic #: 4
What was the original planned duration for Activity A through Activity G?

Suggested Answer: C Vote an answer

by RP at Feb 01, 2024, 11:51 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
RP
2024-02-01 11:51:49
Selected Answer: D
Earlier table shows Original Duration of all activities is 26.
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.