Exam AACE-PSP Topic 5 Question 33 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 33
Topic #: 5
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

Suggested Answer: D Vote an answer

* Each crane can perform 30 lifts per day with a 1.75 cubic yard bucket. For 3 cranes over 5 days: Concrete volume per day=3 cranes×30 lifts/crane/day×1.75 CY/lift.\text{Concrete volume per day} = 3 \text{ cranes} \times 30 \text{ lifts/crane/day} \times 1.75 \text{ CY/lift}.Concrete volume per day=3 cranes×30 lifts/crane/day×1.75 CY/lift. Daily volume=157.5 CY/day.\text{Daily volume} = 157.5 \text{ CY/day}.Daily volume=157.5 CY/day. Over 5 days: Total volume=157.5×5=306 CY.\text{Total volume} = 157.5 \times 5 = 306 \text{ CY}.Total volume=157.5×5=306 CY.
* Reference: PSP Study Guide, Section 1.3.7 - Resource Calculations, demonstrates how crane capacity and lift productivity are incorporated into project planning.

by vasikhali at May 21, 2026, 11:30 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
vasikhali
2026-05-21 23:30:10
157.5x5 is not equal to 306. PLease correct.
upvoted 1 times
...