Exam CCP Topic 5 Question 171 Discussion

Actual exam question for AACE International's CCP exam
Question #: 171
Topic #: 5
____________is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts.

Suggested Answer: A Vote an answer

Percent complete is a measure used in project management to quantify the progress of a project. It is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts. This metric provides an indication of how much work has been completed in relation to the total planned work.
Option B: Cost to complete refers to the estimated cost required to finish all remaining project work.
Option C: Earned value is a key metric in Earned Value Management (EVM) that represents the value of the work actually performed.
Option D: Forecast refers to predicting future project performance and outcomes based on current data and trends.
Therefore, A. Percent complete is the correct answer as it accurately describes the ratio of earned work hours or dollars to budgeted work hours or dollars.

by Angelo at Feb 15, 2025, 12:02 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.