Question #: 10
Topic #: 1
Your team switched to using story points for estimation in the last 2 months and their sprints are 2 weeks long.
Which chart can definitely help you determine the average effort that the team can deliver during each sprint?

Suggested Answer: A Vote an answer

The Velocity Chart shows the amount of story points completed in each sprint, allowing you to determine the average effort the team can deliver. It's specifically designed to track estimation units like story points across completed sprints.

by Colin at May 14, 2025, 07:49 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.