Exam CTS Topic 2 Question 190 Discussion

Actual exam question for AVIXA's CTS exam
Question #: 190
Topic #: 2
Upon completion of hardware installation and configuration for a new deployment, the NEXT thing the AV Project Manager should have scheduled is

Suggested Answer: B Vote an answer

Upon completion of hardware installation and configuration for a new deployment, the next thing the AV Project Manager should have scheduled is testing and verification. This step ensures that all installed equipment functions correctly and meets the project specifications. It involves checking system performance, resolving any issues, and confirming that the setup works as intended. Axis Technology Specialist documentation underscores the critical role of thorough testing and verification in delivering a successful AV project.
Top of Form
Bottom of Form

by Penelope at Jul 15, 2026, 08:45 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.