Exam Construction-Manager Topic 1 Question 24 Discussion

Actual exam question for CMAA's Construction-Manager exam
Question #: 24
Topic #: 1
The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?

Suggested Answer: A Vote an answer

According to theCMAA Construction Management Standards of Practice (SOP), withinContract AdministrationandProject Closeout, theConstruction Manager (CM)is responsible for coordinating all activities related to project turnover, including ensuring that spare parts, warranties, guarantees, and maintenance manuals are transferred properly to the owner.
CMAA states:
"The Construction Manager shall coordinate and verify that all deliverables required by the contract, including spare parts, warranties, record drawings, and operation and maintenance manuals, are received, reviewed, and transmitted to the Owner prior to project closeout." While thecontractoris responsible forprovidingthe spare parts and warranties per the contract, theCMis explicitly tasked withcoordinatingthe transfer and verifying completion. Regulatory agencies do not perform this function, commissioning authorities (CxA) focus on system performance, and the designer's role is typically limited to verification or approval of submittals-not physical coordination.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Contract Administration, Section: "Project Closeout and Turnover." CMAA CM Study Guide, Contract Administration Domain, Objective 5.6: "Coordinate turnover, documentation, and warranties."

by Rupert at Mar 13, 2026, 04:42 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.