Here are all the actual test exam dumps for IT exams. Most people prepare for the actual exams with our test dumps to pass their exams. So it's critical to choose and actual test pdf to succeed.

Exam Construction-Manager Topic 1 Question 25 Discussion

Actual exam question for CMAA's Construction-Manager exam
Question #: 25
Topic #: 1
Who owns the float in a typical project critical path schedule?

Suggested Answer: C Vote an answer

According toCMAA Time Managementstandards,floatis defined as the amount of time an activity can be delayed without affecting the overall project completion date. The SOP specifies:
"Float is a shared resource belonging to the project as a whole. It is not owned exclusively by any single party
- owner, contractor, or construction manager."
This principle ensures fair schedule management and prevents disputes. Both the CM and the contractor should work collaboratively to optimize float use for the benefit of the entire project. Contract documents (e.
g., general conditions) may further define float management policies, but unless specified otherwise, float is treated asa project resource, not the property of any one participant.
Therefore, the correct answer isC. Project.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Time Management, Section: "Float Ownership." CMAA CM Study Guide, Time Management Domain, Objective 5.3: "Manage schedule float as a shared project resource."

by Hugo at Mar 04, 2026, 07:44 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.