Exam Construction-Manager Topic 1 Question 30 Discussion

Actual exam question for CMAA's Construction-Manager exam
Question #: 30
Topic #: 1
Which delivery method, if not properly coordinated, introduces the strong possibility of work scope being duplicated or even omitted?

Suggested Answer: C Vote an answer

TheCMAA Standards of Practiceexplain thatMulti-Prime deliveryinvolves multiple contractors each working under separate contracts directly with the Owner. The absence of a single point of contractual coordination can result inscope overlaps or gapsif the CM or Owner does not maintain tight coordination among all primes.
As noted in the SOP:
"The potential for duplication or omission of work scope is greatest in a multi-prime contracting arrangement, where the responsibility for interfaces between contracts must be clearly defined and managed by the Construction Manager." This risk is unique to the Multi-Prime method because, unlike CMAR or Design-Build, there isno single entity responsible for all construction coordination.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 2 - Project Management, Section: "Project Delivery Methods," pp. 19-20.
CMAA Study Guide, Project Management Domain, Objective 2.1.

by Wanda at Apr 05, 2026, 11:00 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.