Exam Construction-Manager Topic 1 Question 55 Discussion

Actual exam question for CMAA's Construction-Manager exam
Question #: 55
Topic #: 1
Which of the following provides details about the front-end activities of the project during the pre-design and design phases, and highlights major project milestones such as substantial and final completion?

Suggested Answer: B Vote an answer

CMAA's Time Management guidance describes theMaster Scheduleas the overall controlling schedule for the project's life cycle, which includes many elements. It also specifically notes that theMilestone Scheduleis a subset or extract that highlights the key events or decision points:
"The Milestone Schedule acts as a 'pull-out' from the Master Schedule. The purpose of a Milestone Schedule is to highlight the key events in a project, as an executive-level summary. ... The Master Schedule highlights major project milestones and details the front-end activities of the project during thePre-Design and Design phases." Thus, while the Master Schedule covers everything, the Milestone Schedule is the one thatprovides details about front-end activities and highlights major milestones, exactly as asked.

by Enoch at Jun 18, 2026, 09:24 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.