Question #: 206
Topic #: 5
Both the facility and information technology managers are asked to assign staff to work together on a major project. Halfway through the project, the managers observe that the team is in a win-lose power struggle because of divergent views among team members. How should the facility and information technology managers initially intervene?

Suggested Answer: A Vote an answer

Reestablishing meeting guidelines (A)is the best way to address awin-lose power struggle, ensuring structured communication and conflict resolution.
* Clearly defining roles and expectationsprevents misunderstandings and fosters collaboration.
* Reassigning project managers (B)can disrupt continuity and may not resolve underlying team conflicts.
* Assigning members with similar personalities (C)can limit diverse problem-solving perspectives.
* Adding more members (D)might increase complexity without addressing root causes.

by Astrid at Feb 10, 2026, 10:08 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.