Question #: 43
Topic #: 5
The building automation systems (BAS) experienced a power loss. The systems are now back online and are accessible by remote monitoring controls. From a remote login, you observe that the indoor air temperatures are warmer than the settings. What should you do?

Suggested Answer: C Vote an answer

When aBuilding Automation System (BAS)comes back online after a power loss,physical verification of HVAC equipment operation is essentialto:
* Confirm system restart success- Some components may not fully reboot.
* Check for mechanical failures- Power loss could trigger equipment malfunctions.
* Avoid incorrect system readings- Remote monitoring may not reflect actual conditions.
Lowering temperature settings (Option A) isineffectivebecause it will not speed up cooling. Calling an onsite occupant (Option B) provideslimited insightinto the system's condition. While installing agenerator (Option D)is along-term solution, it does notaddress the immediate issue.

by Clifford at Mar 10, 2026, 11:16 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.