Exam CFM Topic 8 Question 11 Discussion

Actual exam question for IFMA's CFM exam
Question #: 11
Topic #: 8
You manage a design-build project to renovate a new office space, including infrastructure upgrades. At the
60% design phase, the design-build contractor's project estimate is over budget and contingency. What should be done first to address the issue?

Suggested Answer: D Vote an answer

Thefirst step should be to investigate the reasons for being over budget (D)before making major project changes.
* A cost overrun could be due to inaccurate estimates, scope changes, or unforeseen conditions.
Understanding the cause allows for informed decision-making.
* Why not other options?
* (A) Delaying a portion of the project may not be necessary and could lead to inefficiencies.
* (B) Seeking a change order should only be done after understanding why costs have increased.
* (C) Removing infrastructure upgrades without proper evaluation could negatively impact long-term functionality.

by Boyd at Feb 20, 2026, 06:00 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.