Question #: 609
Topic #: 5
There are many stakeholders that need to be involved in the allocated requirements. One of the stakeholders in the task will be responsible for verifying released and solution components. Which stakeholder has this responsibility?

Suggested Answer: D Vote an answer

Explanation
Tester is the stakeholder that will be responsible for verifying releases and solution components.
Answer B is incorrect. The project manager is responsible for the work being done by the project team to complete the solution.
Answer A is incorrect. The project team is technically not a stakeholder in the requirements allocation task.
Answer C is incorrect. Operational support does not have the responsibility of verifying released components.

by Jeff at Sep 19, 2025, 11:22 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.