Harry is the project manager of HDW project. He has identified a risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. What type of risk response is Harry implementing?

Suggested Answer: A Vote an answer

is incorrect. Avoidance removes the risk event entirely either by adding additional steps to avoid the event or reducing the project scope. Answer:C is incorrect. Mitigation are actions that Harry's project team could take to reduce the probability and/or impact of a risk event. Answer:B is incorrect. Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs. Here Harry is not accepting this risk event; he does not want anyone of his team to become injured so he's transferring the event to professional vendor.

by Hugo at Jun 27, 2026, 10:06 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.