Exam PfMP Topic 7 Question 108 Discussion

Actual exam question for PMI's PfMP exam
Question #: 108
Topic #: 7
Along your portfolio lifecycle, you have been conducting multiple review meetings to ensure continuation from one phase to another and to ensure the alignment and value delivery, in addition to communicating decisions and valuable information to the related stakeholders. Changes to the approach of portfolio governance may be a result of review meetings. Which of the following options include updates to the governance model?

Suggested Answer: A Vote an answer

Explanation
The governance model is part of the portfolio management plan; the scenario in this question is directly related to the updates on the governance model.

by Ursula at May 11, 2024, 12:39 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.