Actual exam question for PMI's PfMP exam Question #: 177 Topic #: 7
While defining the portfolio, a portfolio manager does a preliminary comparison of all inventoried portfolio components against the portfolio component definition. For this, the descriptors of each portfolio component are used in order to compare it to other components. Which of the following is not a component key descriptors?
Explanation The key descriptors ensure that all portfolio components are comparable. Descriptors and criteria may be used for filtering or eliminating new portfolio components by having associated acceptance levels. Key descriptors include: Portfolio component number, Portfolio component code, Portfolio component description, Type of portfolio component, Strategic goals supported, Quantitative benefits, Qualitative benefits, Portfolio component customer, Portfolio component sponsor, Key stakeholders, and Resources required. Urgency is an evaluation criteria.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Is the comment made by USERNAME spam or abusive?
Commenting
In order to participate in the comments you need to be logged-in.
You can sign-up / login
(it's free).
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).