Exam PMI-CPMAI Topic 2 Question 95 Discussion

Actual exam question for PMI's PMI-CPMAI exam
Question #: 95
Topic #: 2
A team is running a forecasting project and wants to use previous user data to better predict future outcomes. However, the team does not have access to all the data they need.
Which action should the project manager take?

Suggested Answer: B Vote an answer

CPMAI explicitly frames AI and forecasting projects as iterative and incremental, not rigid, one-shot efforts. The methodology allows teams to progress through phases with the understanding that they may loop back when new data or insights become available. In a forecasting project where not all desired historical user data is accessible yet, the recommended approach is to move forward with what is available, while planning and documenting assumptions about missing data and potential impacts.
PMI/CPMAI guidance stresses that waiting for "perfect" data can stall value delivery and increase project risk. Instead, early iterations using partial but representative data help validate the problem framing, test pipelines, and surface data-access issues early, while governance and data owners work on unlocking additional datasets. The key is to acknowledge explicitly that the project is iterative: you may return to earlier data understanding and preparation steps as new data becomes available. This is exactly what option B describes-moving forward while anticipating additional access and leveraging an iterative lifecycle to revisit earlier steps-rather than freezing the project (C) or blindly pressing ahead without a plan (A or D).

by Eve at May 03, 2026, 07:33 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.