Exam PMI-RMP Topic 6 Question 93 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 93
Topic #: 6
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?

Suggested Answer: B Vote an answer

Explanation
The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.

by Leopold at Apr 20, 2024, 04:05 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.