Exam PMO-CP Topic 7 Question 46 Discussion

Actual exam question for PMI's PMO-CP exam
Question #: 46
Topic #: 7
During a session on stakeholder engagement, the PMO team is discussing how to collect and prioritize stakeholder benefit expectations to guide their strategy. The team debates the best approach to ensure that stakeholder needs are effectively addressed without compromising the PMO's alignment with organizational goals. When collecting stakeholders' benefits expectations, what should the PMO do?

Suggested Answer: A Vote an answer

Classifying stakeholders by relevance and influence allows the PMO to prioritize critical expectations without spreading resources too thin. This approach balances individual needs with organizational alignment, ensuring that the most impactful benefits guide the PMO's strategy.
References:
* PMI's Stakeholder Management Principles.
* PMBOK Guide, 7th Edition - Techniques for stakeholder prioritization.

by Truman at Dec 22, 2024, 02:58 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.