Exam PMP-JPN Topic 5 Question 47 Discussion

Actual exam question for PMI's PMP-JPN exam
Question #: 47
Topic #: 5
適応型アプローチの経験がない組織が、社内事業部門への価値提供のスピードを向上させるため、アジャイル手法の導入を検討している。この変革を円滑に進めるため、プロジェクトマネージャーを支援するアジャイル専門家が起用された。
プロジェクトマネージャーは何をすべきでしょうか?

Suggested Answer: D Vote an answer

The correct answer is D because the scenario requires disciplined adaptive delivery rather than an immediate, informal, or purely administrative reaction. The selected response - D. Collaborate with the agile expert to implement a tailored strategy. - directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to protect the feedback loop, keep prioritization transparent, and route product decisions through the accountable role.
This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision- quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK Guide Eighth Edition topics: people, adaptive delivery, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.

by zankure at Aug 12, 2026, 05:44 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
zankure
2026-08-12 17:44:08
Selected Answer: D
D is correct.
upvoted 1 times
...