Question #: 1051
Topic #: 1
A project manager is replaced midway through a very complex technical project. Two weeks after taking over the project the new project manager discovers that the key deliverables have yet to be defined, despite an imminent phase deadline. The project manager creates a change request for project insurance.
Which risk management response is the project manager using?

Suggested Answer: A Vote an answer

by Zara at Apr 15, 2026, 08:02 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.