Exam PMP Topic 1 Question 864 Discussion

Actual exam question for PMI's PMP exam
Question #: 864
Topic #: 1
During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule.
What should the project manager do first?

Suggested Answer: A Vote an answer

by Ziv at Sep 08, 2024, 03:13 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.