Exam PMP Topic 2 Question 1011 Discussion

Actual exam question for PMI's PMP exam
Question #: 1011
Topic #: 2
The team members on your project have been complaining that they do not have any sense of identity as a team because they are located in different areas of the building. To remedy this situation, you developed a project logo and had it printed on T-shirts to promote the project, but this action has not worked. Your next step is to______________

Suggested Answer: C Vote an answer

Explanation/Reference:
Explanation:
Collocating team members, even on a temporary basis, enhances communications, thereby contributing to improved project performance. In addition, the "team meeting room" (often called a `war room') provides a sense of identity to the project team and raises the visibility of the project within the organization. Creating a newsletter is simply applying another organizational process asset, which typically has proven ineffective.

by Barton at Jun 06, 2026, 09:55 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.