Question #: 1115
Topic #: 2
The project scope statement should be used in the identify risk process because it______________

Suggested Answer: A Vote an answer

Explanation/Reference:
Explanation:
Project assumptions, which should be enumerated in the project scope statement, are areas of uncertainty, and as such are potential causes of project risk. The scope statement and the WBS are part of the scope baseline, an input to identify risks.

by Mildred at Jun 23, 2026, 01:28 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.