Question #: 516
Topic #: 2
A software development project is about to start. The product owner and project manager cannot agree on which programming language to use from the available two. The company lacks experienced developers in the product owner's preferred language; however, they are very skilled in the other language.
What should the project manager do?

Suggested Answer: C Vote an answer

by Abraham at Jun 04, 2026, 08:46 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.