Question #: 202
Topic #: 1
While facilitating Program Increment (PI) Planning readiness activities, the Release Train Engineer (RTE) notices a Feature that is risky to the teams because the technology is new. Which of the following could reduce the risk?

Suggested Answer: B Vote an answer

In SAFe, when a Release Train Engineer (RTE) identifies a feature that is risky due to new technology, one of the strategies to reduce the risk is to coach the teams to create exploration Enablers. Exploration Enablers are a type of backlog item that supports research, prototyping, and other activities needed to develop an understanding of customer needs and the technology itself2. This approach allows teams to explore and gain familiarity with the new technology in a controlled environment, reducing uncertainty and risk before committing to the full implementation during Program Increment (PI) Planning2. It is part of the Continuous Exploration process, which is key to fostering innovation and aligning the solution with customer needs1.

by Pearl at Apr 02, 2024, 01:57 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.