Question #: 33
Topic #: 1
What action can result in reduced collaboration between teams during the Program Increment (PI) Planning event?

Suggested Answer: C Vote an answer

Starting an Agile Release Train (ART) without a System Team in place can lead to reduced collaboration between teams during the Program Increment (PI) Planning event. The System Team plays a vital role in supporting the ART by addressing system-level issues and enabling integration across different teams.
Without this support, teams may face challenges in integrating their work with others, leading to silos and reduced collaboration. The presence of a System Team is essential for facilitating effective communication and collaboration during PI Planning, ensuring that teams can work together efficiently and that dependencies are managed properly12.

by lolly at Jan 18, 2025, 08:28 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
lolly
2025-01-18 08:28:04
Selected Answer: D
the SAFe practice test states this as the correct answer
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.