Exam SAFe-RTE Topic 3 Question 154 Discussion

Actual exam question for Scaled Agile's SAFe-RTE exam
Question #: 154
Topic #: 3
What are two ways program risks can be categorized? (Choose two.)

Suggested Answer: C,E Vote an answer

Program risks can be categorized based on whether they are Deferred or Owned. A deferred risk is one that has been identified but is not being actively addressed at the moment, possibly due to prioritization of other risks or resource constraints. An owned risk is one that has been assigned to an individual or team who is responsible for managing and mitigating the risk. This categorization helps in tracking and accountability within the SAFe framework.

by koley.debapriyo at Nov 24, 2024, 04:45 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
koley.debapriyo
2024-11-24 04:45:45
Selected Answer: DE
By Applying ROAM - Resolved and Owned seems to be the correct answer
upvoted 1 times
...