Exam SP-SAFe-Practitioner Topic 3 Question 172 Discussion

Actual exam question for Scaled Agile's SP-SAFe-Practitioner exam
Question #: 172
Topic #: 3
What is an example of applying cadence-based synchronization in SAFe?

Suggested Answer: D Vote an answer

Explanation
Conducting a PI Planning event is an example of applying cadence-based synchronization in SAFe. A PI Planning event is a two-day face-to-face or virtual meeting where all the members of an ART and Solution Train collaborate to align on a common vision, mission, and backlog, and plan the work for the next Program Increment (PI). A PI is a fixed timebox of 8 to 12 weeks that provides a regular cadence for delivering value.
The PI Planning event is synchronized across all the teams and trains in the portfolio, and it occurs at the beginning of every PI. The PI Planning event enables the ART and Solution Train to achieve alignment, collaboration, synchronization, and commitment, as well as to identify and address risks and dependencies. References: = PI Planning - Scaled Agile Framework, Exam Study Guide: SP (6.0) - SAFe Practitioner

by Kama at Apr 18, 2025, 08:33 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.