Exam PSM-III Topic 1 Question 18 Discussion

Actual exam question for Scrum's PSM-III exam
Question #: 18
Topic #: 1
The definition of "Done" describes the work that must be completed for every Product Backlog item before it can be deemed releasable. What should the Development Team do when, during the Sprint, it finds out that a problem outside of their control blocks them from doing all this work?

Suggested Answer:

When the Development Team discovers during a Sprint that a problemoutside of their controlprevents them from completing all work required by theDefinition of Done, this situation must be addressed through transparency, inspection, and adaptation, rather than by lowering standards.
1. Make the Impediment Transparent Immediately
The Development Team shouldmake the issue visible as soon as it is discovered. This includes:
* Raising it in theDaily Scrum,
* Clearly stating how it impacts the Sprint Goal and the Definition of Done.
Transparency is critical so that inspection and adaptation are based on reality, not assumptions.
2. Do Not Compromise the Definition of Done
The Definition of Done mustnot be relaxed or bypassedto "get something done." Lowering quality destroys transparency and creates false progress. If the Definition of Done cannot be met, the work isnot Doneand should not be considered releasable.
3. Collaborate to Adapt the Sprint Backlog
The Development Team should collaborate with theProduct Ownerto inspect the impact and adapt the Sprint Backlog. This may include:
* Removing or adjusting affected Product Backlog Items,
* Focusing on work that can still meet the Definition of Done,
* Preserving theSprint Goal, if possible.
4. Escalate the Impediment Through the Scrum Master
Because the problem is outside the team's control, it qualifies as animpediment. The Scrum Master must help remove or mitigate it by working with the organization or external parties. If the impediment cannot be resolved quickly, its impact should be addressed in planning and stakeholder communication.

by Maxwell at Feb 22, 2026, 12:20 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.