Exam SSM Topic 1 Question 19 Discussion

Actual exam question for Scrum's SSM exam
Question #: 19
Topic #: 1
Team A has decided to use the IP Iteration to continue the finalizing Feature delivery work they have been working on for the past two IP Iterations. What is one effect Team A might experience by continuing to stay heads-down rather than using the IP Iteration as intended?

Suggested Answer: D Vote an answer

The Innovation and Planning (IP) Iteration is designed to give teams space for innovation, exploration, learning, and improvement, not for continuing regular feature work. When a team misuses the IP Iteration to "catch up" on delivery, it misses the opportunity to experiment, innovate, and explore new ways to deliver solutions more effectively.
This reduces the long-term adaptability and creativity of the team, limiting their ability to introduce process or technical improvements that could increase efficiency in future PIs. The IP Iteration is also a time for the Inspect and Adapt event and PI Planning, both of which are critical to continuous improvement.
From SAFe guidance:
"The IP Iteration provides dedicated time for innovation and planning. Using it for normal work diminishes opportunities to innovate, learn, and explore new approaches." Therefore, the correct answer is D. They could lose an opportunity to consider new approaches to Solution delivery.

by Deloitte at Apr 30, 2026, 05:28 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
Anthony
2026-07-31 05:06:32
Selected Answer: D
The correct answer is D. They could lose an opportunity to consider new approaches to Solution delivery.

Reason for the Correct Answer:
The IP (Innovation and Planning) Iteration in SAFe serves a dedicated purpose: providing uninterrupted time for innovation, infrastructure improvements, continuing education, and PI (Program Increment) planning. Using it merely as an extension to finish delayed regular feature work means the team misses the dedicated window needed to explore new technologies, innovative ideas, and better approaches to delivering solutions.

Explanation of the Options:
- A. They could lose an opportunity to build relationships across the teams (Incorrect): While cross-team collaboration happens during IP Iteration events like PI Planning, the primary direct consequence of failing to use the IP Iteration for its main intent (innovation and improvement) is the loss of time for exploring better solution delivery methods.
- B. They could lose an opportunity to manage risks and communication within the ART (Incorrect): ART-wide risks and synchronization are typically handled continuously and during PI Planning, rather than being the specific primary focus lost by using IP time for feature work.
- C. They could lose an opportunity to collaborate with other developers and understand dependencies (Incorrect): Dependency management and collaboration occur throughout the regular Iterations of the PI, not uniquely within the IP Iteration.
- D. They could lose an opportunity to consider new approaches to Solution delivery (Correct): The core intent of the IP Iteration is to allow space for innovation, learning, and exploring new methods or technical improvements. Staying heads-down on feature delivery directly robs them of this opportunity.
upvoted 1 times
...
Deloitte
2026-04-30 17:28:31
Selected Answer: D
D is right answer.
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.