Exam SSM Topic 1 Question 38 Discussion

Actual exam question for Scrum's SSM exam
Question #: 38
Topic #: 1
What is one anti-pattern of the Inspect and Adapt?

Suggested Answer: A Vote an answer

One anti-pattern of the Inspect and Adapt (I&A) is to have no actionable improvement Features created as a result of the problem-solving workshop. This is considered an anti-pattern because the main goal of the I&A workshop is to identify and address the systemic issues that are limiting the effectiveness of the Agile Release Train (ART). The workshop should produce one or more improvement Features that are added to the ART backlog and prioritized for the next PI Planning event. These Features should be SMART (Specific, Measurable, Achievable, Relevant, and Time-bound) and aligned with the ART vision and goals. Without actionable improvement Features, the ART will miss the opportunity to learn and improve from the feedback and data collected during the PI.
:
Inspect and Adapt - Scaled Agile Framework
Exam Study Guide: SSM (6.0) - SAFe Scrum Master
based on SAFe 60 methodology What is one antipattern of the

by Deloitte at Apr 30, 2026, 05:31 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
Anthony
2026-07-31 05:21:25
Selected Answer: A
Correct Answer is A.
A. No actionable improvement Features are created
Reason (Correct): The primary goal of the I&A event is to identify root causes and create concrete, actionable improvement features that can be added to the Program Backlog for the next Program Increment (PI). If the event ends in discussion without producing any actionable improvements, the core objective of relentless improvement is missed, making this a classic anti-pattern.

Incorrect Options
B. Not enough team members attend the PI System demo
Reason (Incorrect): While broad participation is ideal, attendance fluctuations can happen and can be addressed. The primary anti-patterns of I&A focus on structural failures of the workshop itself (such as failing to produce improvement backlogs) rather than attendance numbers.

C. Too many ideas enter the problem-solving workshop
Reason (Incorrect): Having many ideas or issues raised is actually a sign of engagement. The problem-solving workshop includes steps (like Pareto analysis) to filter and prioritize them, so a large initial volume of ideas is not an anti-pattern.

D. Only one problem is identified by each team in the retrospective
Reason (Incorrect): While teams often identify multiple issues, if a team focuses deeply on a single, high-impact problem to solve, that can still lead to a meaningful and valuable improvement. Identifying only one problem is not inherently an anti-pattern.
upvoted 1 times
...
Deloitte
2026-04-30 17:31:39
Selected Answer: A
A is right answer.
upvoted 1 times
...