Exam SSM Topic 1 Question 73 Discussion

Actual exam question for Scrum's SSM exam
Question #: 73
Topic #: 1
In the context of a Team Increment, every Iteration each team plans, builds, tests, integrates, and?

Suggested Answer: C Vote an answer

by Brandon at Jul 07, 2026, 07:24 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
Pepsi
2026-08-01 05:41:22
Selected Answer: C
C. Review their work

Reason for the Correct Answer:
- C. Review their work: In SAFe, every iteration follows a predictable rhythm where Agile Teams plan, build, test, integrate, and review their work (via the Iteration Review) to gather feedback, inspect progress, and adapt.

Reasons for the Incorrect Answers:
- A. Reorganizes: Teams maintain stability to build trust and high performance rather than reorganizing every single iteration.
- B. Sets new objectives: Objectives are typically set at the Program Increment (PI) level during PI Planning, rather than establishing entirely new high-level objectives every single iteration.
- D. Clears out the backlog: Backlog management and refinement are ongoing continuous processes, not something done to completely clear out the backlog at the end of every iteration.

Reference:
Scaled Agile, Inc. - SAFe Iteration Execution
https://scaledagileframework.com/
upvoted 1 times
...