Consider the following ADM phases objectives.
Objective
1- Determine whether an incremental approach is required, and if so identify Transition Architectures that will deliver continuous business value
2- Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D
3- Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan
4- Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders Which phase does each objective match?

Suggested Answer: B Vote an answer

According to the TOGAF standard, the objectives of each ADM phase are as follows1:
* Phase E: Opportunities and Solutions
o Determine whether an incremental approach is required, and if so identify Transition Architectures that will deliver continuous business value o Identify and group major work packages within the Architecture Roadmap o Identify and group major implementation projects to realize the Architecture Roadmap o Identify dependencies between increments and projects o Estimate cost, benefit, and risk at a high level for each increment and project o Conduct initial prioritization and sequencing of the Architecture Roadmap and projects
* Phase F: Migration Planning
o Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D o Confirm the Transition Architectures with relevant stakeholders o Create the Implementation and Migration Plan, including Transition Architectures, work packages, projects, and other activities o Confirm and agree the Architecture Roadmap and Implementation and Migration Plan with relevant stakeholders
* Phase G: Implementation Governance
o Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan o Ensure conformance with the Target Architecture by implementation projects o Perform appropriate Architecture Governance functions for the solution and any implementation-driven architecture Change Requests o Ensure that the architecture lifecycle is maintained o Ensure that the Architecture Governance Framework is executed
* Phase H: Architecture Change Management
o Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders o Manage risks and issues related to the Architecture Roadmap and Implementation and Migration Plan o Monitor the implementation projects and Transition Architectures o Manage changes to the architecture baseline o Manage changes to the Architecture Capability Therefore, the correct matching of the objectives and the phases is:
* 1G: Determine whether an incremental approach is required, and if so identify Transition Architectures that will deliver continuous business value
* 2E: Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D
* 3F: Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan
* 4F: Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders

by Gabriel at Dec 07, 2024, 06:53 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
msayed.asm
2025-02-03 00:46:39
correct answer is C
upvoted 1 times
...
aatandon
2024-12-30 10:06:54
The correct order should be 1E - 2E - 3F - 4F

The objectives of Phase E are to:

Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D
Determine whether an incremental approach is required, and if so identify Transition Architectures that will deliver continuous business value
Define the overall Solution Building Blocks (SBBs) to finalize the Target Architecture based on the ABBs

The objectives of Phase F are to:

Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan
Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise's approach to managing and implementing change in the enterprise's overall change portfolio
Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders