Exam OGEA-101 Topic 7 Question 44 Discussion

Actual exam question for The Open Group's OGEA-101 exam
Question #: 44
Topic #: 7
Complete the following sentence. In the ADM, documents which are under development and have not undergone any formal review and approval process are called______ Documents which have been reviewed and approved are called ______

Suggested Answer: B Vote an answer

According to the TOGAF Standard, 10th Edition, documents which are under development and have not undergone any formal review and approval process are called draft documents, while documents which have been reviewed and approved are called approved documents 1. Draft documents are typically marked with a version number of 0.x, indicating that they are incomplete or provisional. Approved documents are typically marked with a version number of 1.0 or higher, indicating that they have been finalized and authorized. The other options are not correct, as they are not the terms used by the TOGAF Standard to distinguish between documents under development and documents that have been reviewed and approved. The terms "finalized", "concept", "deliverable", and "Version 0.1" and "Version 1.0" are not specific to the TOGAF Standard, and they may have different meanings or interpretations in different contexts. Reference: 1: TOGAF Standard, 10th Edition, Part II: Architecture Development Method, Chapter 7: Applying Iteration to the ADM, Section 7.2.3 Document Categorization.

by Hiram at Feb 26, 2025, 03:47 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
ubiquituz
2025-08-24 04:45:27
B


In the ADM, documents which are under development and have not undergone any formal review and approval process are designated “draft”
Conversely, documents which have been reviewed and approved are designated “approved” in accordance with the governance practices of the organization.
Approved does not necessarily mean finalized.
upvoted 1 times
...
ubiquituz
2025-08-15 11:41:48
C Concept documents are under development and have not yet been formally reviewed or approved.

Once a document has undergone review and approval, it becomes a deliverable — a formal output of the architecture development process.
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.