Consider the following ADM phases objectives.

Which phase does each objective match?

Suggested Answer: B Vote an answer

1E: To identify delivery vehicles (projects programs portfolios) that will deliver the Target Architecture 2F:
To confirm readiness and ability to undergo change 3E: To determine whether an incremental approach is required and if so identify Transition Architectures that will deliver continuous business value 4G: To perform appropriate governance functions while the solution is being implemented Reference: The TOGAF Standard | The Open Group Website, Section 3.2 ADM Phases.

by pablo_9028 at Jan 07, 2025, 01:30 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
pablo_9028
2025-01-07 01:31:31
Selected Answer: D
TOGAF Standard C220 - ADM
The objectives of Phase F are to:
■ Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan
■ Ensure that the Implementation and Migration Plan is coordinated with the enterprise’s approach to managing and implementing change in the enterprise’s overall change portfolio
■ Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders
upvoted 1 times
...
pablo_9028
2025-01-07 01:30:44
Right answer is D: 1F-2F-3E-4G

TOGAF Standard C220 - ADM
The objectives of Phase F are to:
■ Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan
■ Ensure that the Implementation and Migration Plan is coordinated with the enterprise’s approach to managing and implementing change in the enterprise’s overall change portfolio
■ Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.