Microsoft Managing Projects and Portfolios with Microsoft PPM - 070-348 Free Exam Questions

QUESTION NO: 1
You are a resource manager in an organization that uses Microsoft PPM for resource management. You manage two teams, one local and one remote. Project managers are instructed to always submit resource requests based on generic roles instead of named resources. Resource managers replace the generic resources with available named resources.
Project managers must not start work on projects that have generic resources assigned.
You need to replace proposed requests with committed, named resources.
Which three actions should you perform? Each correct answer presents part of the solution.

Correct Answer: A,C,E Vote an answer
QUESTION NO: 2
DRAG DROP
You are managing a Biothermal Ear Heating System for Helmets project using Microsoft Project.
You must use the appropriate resource types for tasks in your project schedule.
Match each resource type to its definition.
To answer, drag the appropriate resource type from the column on the left to its definition on the right.
Each resource may be used once, more than once, or not at all. Each correct match is worth one point.
Correct Answer:
QUESTION NO: 3
HOTSPOT
You use Microsoft PPM to manage projects. You plan to use milestones in a project.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
Correct Answer:
QUESTION NO: 4
You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent.
The IT manager adds an additional business driver that has a priority value set to 30 percent.
You need to create a new prioritization that includes the additional business driver.
What should you do?

Correct Answer: A Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 5
DRAG DROP
You are project manager in your company's PMO. You have permission to manage the
Enterprise Global view in Microsoft PPM. Your organization works with many large multiyear projects often managed by more than one project manager.
You need to provide an Enterprise Global view that displays the fields necessary for your colleagues to control whether a task is published, who will be responsible for sending the task updates for the task, and who is responsible for approving updates from resources.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Correct Answer:

QUALITY AND VALUE

Actual4test Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our Actual4test testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

Actual4test offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.