You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects.
Identify three conditions that must be met for exporting milestone tasks.
(Choose three.)
Response:
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem.
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction''s business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client''s expectations. Identify two valid rules based on which cost association works.
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost of each asset.
Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement.
(Choose the best answer.)
Response:
Which three tasks can be performed using the project requirements work area? (Choose three.)
You are implementing Project Portfolio Management for a global professional services organization. In their Consulting Services line of business, it is common to use resources from different business units based on the skills required. Therefore, cross-charge transactions happen between business units within the same legal entity. Transfer price calculations need to be based on raw costs, with no further adjustments to transfer price.
Identify two setups that can drive this borrowed and lent agreement.