Oracle Manufacturing Cloud 2020 Implementation Essentials - 1z0-1075-20 Free Exam Questions

QUESTION NO: 1
The Manufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day and Night Shift.
Identify the correct sequence of steps to achieve this requirement.

Correct Answer: B Vote an answer
QUESTION NO: 2
As a production supervisor, you require immediate access to critical shop floor execution systems to take action while on the go.
Which four work order related actions can be taken in the Manufacturing Supervisor mobile application?

Correct Answer: C,D,E,F Vote an answer
QUESTION NO: 3
You want to use a predefined Standard Operation in a Work Definition, but you also want to change the usage of the Standard Operation resource. Identify the setup required.

Correct Answer: A Vote an answer
QUESTION NO: 4
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.

Correct Answer: D Vote an answer
QUESTION NO: 5
A user wants to transfer the work order status updates and resource transaction data for costed resources to Cost Management.
Which scheduled process should you run to achieve this requirement?

Correct Answer: C Vote an answer
QUESTION NO: 6
In your customer's manufacturing facility, different types of Movement Requests are created. Key manufacturing components are issued to the work orders form the manufacturing subinventory. The manufacturing subinventory receives its supplies form the Warehouse subinventory through automatically created Movement Requests.
Which type of Movement Requests should you use to fill the manufacturing subinventory form the Warehouse subinventory?

Correct Answer: D Vote an answer
QUESTION NO: 7
Identify two conditions that should be met at the same time for a Standard Operation to be called an Optional Operation.

Correct Answer: A,D Vote an answer

QUALITY AND VALUE

Actual4test Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our Actual4test testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

Actual4test offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.