Identify the correct statement about setting lead time information In the Sublnventory Definition form.
You are using Manufacturing Work Order Scheduling In Unconstrained Plans at your client site. Your client Is confused about some of the basic concepts, and you are asked to clarify them.
Identify two correct statements about Manufacturing Work Order Scheduling In Unconstrained Plans, which you will relate to your client.
Identify two attributes that are unique to Global Forecast when compared with Local Forecasts.
Exhibit.

You define a Supply Chain plan of type "Manufacturing Plan." In the Plan Options Main tab, you select Planned Items as "Demand schedule items and all sales orders" and select the Include Critical Components check box.
The Exhibit shows Bills of Material for Items A and
B. It also shows the settings for the Include Sales Order check box on the Plan Options Organizations tabbed page.
Item A has Demand Schedules and Sales Orders for Organizations Ml and M2. Item B has only Sales Orders for Organizations Ml and M2.
Which three statements are correct in the above plan scenario?
Identify four exception messages that are most likely to appear In an unconstrained plan.
Exhibit.

In a manufacturing environment where Oracle Shop Floor Management Is used, the production process with Information about Yield (Yld), Net Planning Percent (NPP), Cumulative yield (CY), Reverse Cumulative Yield (RCY) is displayed for a product.
If the order quantity is 100, what is the raw material quantity and resource requirement ASCP will schedule respectively at operation sequence 10?
Identify the three correct statements about the Plan Options Main Tab setup.
Your client is using Global Forecasts. The client's Planning Manager states that Sales Order consumption is not working correctly. Identify two possible causes.
The following is the business scenario at your client site:
1) Your client manufactures goods that can be produced In alternate ways that requires flexible definition of Routings.
2) They have multiple manufacturing Organizations namely Ml, M2, and M3.
3) The future operation details of Jobs need to be stored only In Ml and M3.
4) A complete recommended path for a Job should exist and should be updatable.
Which one will be part of your solution?