You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.
How can you fulfill these requirements in SAP ECC? (Choose two)
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
The availability check during production order creation should use a different scope of check than during order release.
How can you fulfill this requirement?
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
What do you have to consider regarding consumption? (Choose two)