CMAA Certified Construction Manager (CCM) - Construction-Manager Free Exam Questions

QUESTION NO: 1
Which of the following provides details about the front-end activities of the project during the pre-design and design phases, and highlights major project milestones such as substantial and final completion?

Correct Answer: D Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 2
A CM is providing support on a $150 million construction project. The agency has a well-developed safety program; however, the contractor is planning to use an innovative, high-risk method for constructing the project. To minimize the owner's risk, the CM should recommend that the owner

Correct Answer: C Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 3
The current construction market is extremely busy, and the trade/sub-contractors are being very selective in the projects they bid on. What options do owners have when the marketplace is vastly different from when their project was a concept to when its ready to be advertised?

Correct Answer: A Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 4
When developing schedule specifications, which of the following practices should the CM recommend to the Owner to avoid disputes regarding weatherdelays per year?

Correct Answer: B Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 5
Float, date, and duration are examples of

Correct Answer: A Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 6
A program management function that promotes the efficient use of completed projects and/or parts of completed projects to maximize the owner's return on investment is called

Correct Answer: B Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 7
The chief estimator for a construction company is asked to provide an estimate based on known project characteristics, such as square footage and unit prices. The estimator will MOST likely be employing which technique?

Correct Answer: D Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).

QUALITY AND VALUE

Actual4test Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our Actual4test testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

Actual4test offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.