NABCEP PV Installation Professional (PVIP) Board Certification - PVIP Free Exam Questions

QUESTION NO: 1
Per NEC 690.8, a PV source circuit has an Isc of 9.5A. What is the minimum ampacity required for the conductor?

Correct Answer: A Vote an answer
QUESTION NO: 2
A PV system uses 10 AWG USE-2 wire for a 150-foot source circuit run with an Isc of 8A. The terminals are rated at 75°C. What is the ampacity of the conductor after applying NEC temperature and conduit fill adjustments at 35°C?

Correct Answer: B Vote an answer
QUESTION NO: 3
A PV array is installed on a sloped roof with a 6:12 pitch. What is the minimum fastener pullout strength required if the uplift force is 200 lbs per attachment point?

Correct Answer: D Vote an answer
QUESTION NO: 4
A bifacial array gains 15% additional power from rear-side irradiance. If the front-side output is 10 kW, what is the total output?

Correct Answer: B Vote an answer
QUESTION NO: 5
A maintenance inspection reveals cracked module glass. What is the immediate action?

Correct Answer: A Vote an answer
QUESTION NO: 6
A module's Isc is 8.5A at STC. At 1200 W/m², what is the Isc?

Correct Answer: D Vote an answer
QUESTION NO: 7
A site survey indicates a residential roof with a 4:12 pitch facing 20° east of south. The local latitude is 35°N, and the optimal tilt for maximum annual production is equal to latitude. What adjustment should be made to compensate for the roof's orientation and tilt to achieve near-optimal output?

Correct Answer: C Vote an answer
QUESTION NO: 8
During commissioning, a PV system's measured Voc is 10% lower than expected. What is the most likely cause?

Correct Answer: B Vote an answer
QUESTION NO: 9
A site has a known magnetic declination of 14 west. What should the corrected azimuth reading of the array be in order to be facing true south?

Correct Answer: C Vote an answer
QUESTION NO: 10
A 10 kW PV array uses 300W modules with a Voc of 40V and an Isc of 9A. The inverter has a maximum DC input of 600V and 25A. What is the maximum number of modules that can be connected in a single string?

Correct Answer: C Vote an answer
QUESTION NO: 11
When performing a system checkout after completing the installation, what is the SAFEST sequence of tasks to detect installation errors before closing any disconnects to the inverter, charge controller, or batteries?

Correct Answer: D Vote an answer
QUESTION NO: 12
A grid-tied PV system uses a transformerless inverter with a maximum DC input of 1000V. The array consists of 20 modules, each with a Voc of 45V. What is the NEC 690.7 correction factor for a low temperature of -15° C if the temperature coefficient is -0.30%/°C?

Correct Answer: B Vote an answer

QUALITY AND VALUE

Actual4test Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our Actual4test testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

Actual4test offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.